TERR A DC WA LLBOX
2023 -06-20 24/39
5.4.1 Mounting the Terra DC Wallbox
NOTICE
The minimum number of people required to lift and install
the Terra DC Wallbox must be determined based on the
relevant local regulation with taking into account the
maximum allowed weight per person as well as the usage of
the appropriate and suitable lifting equipment. The
definition of the exact lifting equipment and working
method for lifting is the responsibility of the installation
contractor.
1. Carefully lower the Terra DC Wallbox onto its location.
2. Ensure cable(s) are not entrapped.
3. Place the wall frame in the correct position on the wall bearing by aligning the four holes of the
charger with the corresponding holes on the wall bearing.
4. Tighten the four screws with stainless steel 8.8 hexagonal bolts.
5. Place the unit on the wall frame by correctly aligning the 6 bolts (3 for each lateral side).
Mounting
holes
Mounting
holes

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB Terra 24 and is the answer not in the manual?

ABB Terra 24 Specifications

General IconGeneral
BrandABB
ModelTerra 24
CategoryBattery Charger
LanguageEnglish

Related product manuals