9 Commissioning
9.3.5 Heater
Switch off all power supplies and feel by hand that the heater has been warmed up during
earlier tests. Switch on the power afterwards.
Check that the air vents are open.
Remove the drying agent used during transport.
9.3.6 Pressure relay
Check the function as per section 5.3.
9.4 Putting into operation
Put the LOCAL/REMOTE switch to REMOTE. Reset the drag hands.
Make sure that no tools or foreign objects are left in the motor drive cabinet. Close the door.

Table of Contents

Other manuals for ABB UZE

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB UZE and is the answer not in the manual?

ABB UZE Specifications

General IconGeneral
BrandABB
ModelUZE
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals