7 | Commissioning
16 | 32 Instruction Manual R5 RA 0063 F5K_EN_en
7 Commissioning
NOTICE
The machine can be shipped without oil.
Operation without oil will ruin the machine in short time!
Prior to commissioning, the machine must be filled with oil, see Filling Oil [12].
CAUTION
During operation the surface of the machine may reach temperatures of more than 70°C.
Risk of burns!
Avoid contact with the machine during and directly after operation.
CAUTION
Noise of running machine.
Risk of damage to hearing!
If persons are present in the vicinity of a non noise insulated machine over extended periods:
Make sure that ear protection is being used.
Make sure that the installation conditions (see Installation Conditions [10]) are met.
Switch on the machine.
Make sure that the maximum permissible number of starts does not exceed 30 starts per hour.
Those starts should be spread within the hour.
Make sure that the operating conditions comply with the Technical Data [28].
After a few minutes of operation, check the oil level and top up if necessary.
As soon as the machine is operated under normal operating conditions:
Measure the motor current and record it as reference for future maintenance and trouble-
shooting work.
7.1 Version with Oil Return Valve
When the machine runs, oil cannot flow back to the bottom oil receiver and it accumulates in the up-
per chamber of the oil separator.
After 2hours of continuous operation near ultimate pressure, in case of operation in rough vacuum,
after a shorter time:
The machine must be shut down for at least 15 min.
The oil can run down from the upper chamber of the oil separator into the bottom chamber
7.2 Conveying Condensable Vapors
Water vapor within the gas flow is tolerated within certain limits. The conveyance of other vapors
shall be agreed upon with Busch.
If condensable vapors are to be conveyed:
START

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BUSCH R5 RA 0063 F 5K and is the answer not in the manual?

BUSCH R5 RA 0063 F 5K Specifications

General IconGeneral
BrandBUSCH
ModelR5 RA 0063 F 5K
CategoryWater Pump
LanguageEnglish

Related product manuals