11. INSPECTION AND CONFIRMATION AFTER REASSEMBLY
Check that Plunger (A) [59] moves smoothly.
Check that there is no air leakage from each part.
While driving nails with an air pressure of 4.5 kgf/cm
2
(63 psi), check that there is no idle driving and bending
of nails.
Note: Before conducting the driving test, turn Adjuster [44] to the deepest position.
Recheck the tightening torque of each screw.
Check that Pushing Lever (A) [31] slides smoothly.
Check that the machine will not operate only by pulling the Trigger [39]. Also check that the machine will not
operate only by depressing Pushing Lever (A) [31].
Push Nail Stopper (A) [90] and Nail Stopper (B) [92] with fingers to check that they smoothly return to position.
Check that the Feed Piston [64] operates properly at 5 kgf/cm
2
(70 psi. 4.9 bar) (Open the Nail Guide [89] and
perform idle driving.).
Check that the Trigger [39] moves smoothly.
Check that the Adjuster [44] turns smoothly.