LAUNCH 440(440W) 455(455W) Installation Manual
6
3 Tools for installation and
adjustment
To perform the installation and adjustment, please get the
following tools ready:
Tools Model
Leveling Meter For carpentry
Chalk Min. 4.5m
Hammer 1.5kg
Adjustable Wrench 40mm
Open Spanner Set 11mm-23mm
Ratchet Socket Set
Flat Screw Driver 150mm
Rotary hammer Drill 16mm
Alloy Drill-bit
¢16mm
4 Unpacking
l Unpack and remove the packing materials. Inspect the
lift for possible damage or loss of accessories during
transportation.
l Keep the packing materials out of the reach of children to
avoid accident. Packing materials should be disposed
of in a proper way.。
5 Installation
5.1 Precautions for installation
l The wrong installation will cause the lift damage or
personal injury. The manufacturer will not undertake any
responsibilities for any damage caused due to incorrect
installation and usage of this equipment, whether directly
or indirectly.
l The correct installation location shall be on “horizontal”
floor to ensure the horizontal lifting. The slightly slope
floor can be corrected by proper shimming. Any big slope
will affect the level of the lifting. If the floor is of
questionable slope, consider a visual inspection, or pour
a new horizontal concrete slab if possible. Don’t expect to
compensate for the serious slope by shimming.
l Don’t install the lift on any asphalt surface or any surface
other than concrete. The lift must be installed on concrete
floor conforming to the minimum requirement showed in
this manual. Don’t install the lift on the concrete with
seams or crack and defect. Please check together with
the architect.
l Without the written approval of the architect, don’t install
the lift on a second floor with basement.
l Overhead obstruction: The lift installation area can’t have
any overhead obstruction, such as heater, building
support, electrical pipe, etc.
l Concrete drilling test: The installation personnel can test
the concrete thickness at each site by drilling test. If
several lifts are installed at one place, it is preferred to
make drilling test in each site.
l Power supply: Get ready the power supply before the
installation. All the electric wiring and connecting should
be performed by a certified electrician.
5.2 Installation procedures
5.2.1 Overall Positioning
Selecting installation site based on the following conditions::
l If the thickness of the whole ground concrete is greater
than 200mm, the lift can be installed directly.
l If the thickness of the whole ground concrete is less than
200mm, the concrete slab must be made. The minimum
thickness of the concrete slab is 200mm, with 7 days of
minimum curing time.
l The concrete slab shall have steel bar reinforcement and
must be leveled.
l Check the possible obstruction, e.g. low ceiling, top
pipeline, working area, passage, exit, etc.
l Allow enough space around the lift for accessing the
vehicle. (as in Fig. 5)
www.diagtools.eu, Pernavas 43A, Riga, Latvia, LV-1009, +37129416069, info@diagtools.eu