Commissioning and adjusting
Preparations
Before commissioning, check that the heating circuit is filled
and well vented. Check the pipe system for leaks.
Filling and venting the heating medium system
The heating medium system is filled with water to the re-
quired pressure. Vent the system using the venting nipple
on the enclosed flexible hose and possibly the circulation
pump.
9HQWLQJ QLSSOH
Balance temperature
The balance temperature is the outdoor temperature when
the heat pump’s stated output is equal to the building’s
output requirement. This means that the heat pump covers
the whole building’s output requirement down to this tem-
perature. Setting of the balance temperature, additional heat,
is made on channel A5.
Stop temperature
When the stop temperature (channel A7) is set between -7
and -20 °C the flow temperature is limited linearly from -7 °C
/ 58 °C to -20 °C / 50 °C.
Soft-start relay
F2025 is equipped with a soft-start relay (97) that limits the
inrush current for the compressor.
The compressor must not be forced to start with periods
shorter than 1 start per 15 minutes.
Compressor heater
F2025 is equipped with a compressor heater that heats the
compressor before start-up and when the compressor is cold.
The compressor heater must have been connected for6-8
hours before the FIRST start, see the section “Start-up and
inspection”.
NOTE
The compressor heater must have been connected for
6 8 hours before the first start, see the section “Start-
up and inspection”.
Phase sequence control
When starting for the first time or after work on incoming
electricity supply, phase sequence control must be carried
out. This is important because the scroll compressor in F2025
can suffer damage if operated with the incorrect direction
of rotation for too long. See points 10 11 under “Start-up
and inspection”.
NOTE
Check the phase sequence when starting!
F202520
For the Installer
Commissioning and adjusting

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Nibe F2025 and is the answer not in the manual?

Nibe F2025 Specifications

General IconGeneral
BrandNibe
ModelF2025
CategoryHeat Pump
LanguageEnglish

Related product manuals