Soft Starter Startup Manual Sprecher + Schuh Hydraulic Installation
Page 6 © 2021 Smartrise Engineering, Inc. All Rights Reserved January 30, 2021
Figure 6: Example of Construction Wiring
Powering Up
Perform the following to power up the soft starter. Complete the checklist during the
verification process.
1. Apply external power by closing the main disconnect.
2. Close the two-pole breaker and all pushbutton breakers.