18 CGWF-SVX01A-EN
Installation Mechanical
WARNING
Unit Lifting Capacity!
The capacity of the lifting equipment sued must exceed etc. Then end
with failure to use properly sized lifting equipment could result in death
or serious injury or equipment damage.
WARNING
Improper Unit Lifting!
Follow the lifting procedure detailed below. Failure to follow the proper
lifting procedure could result in death or serious injury or equipment
damage.
Lifting Procedure for 20-50 Ton CGWF 20-60 and Ton CCAF Units.
1. Remove the two sheet lifting angles from the skid.
2. Remove the unit from the shipping skid. If absolutely necessary, the chiller can be
pushed or pulled across a smooth surface as long as it is bolted to the shipping
skid.
3. Bolt the lifting angles to the unit as shown in Figure 4. Mount one lifting angle at
each end of the unit using the nuts and bolts provided.
4. Tighten each bolt to 70ft-lbs torque.
5. Verify the lifting angle mounting bolts are tightened to 70ft-lbs torque.
6. Install clevis connectors in the 1-1/4” (32 mm) lifting holes provided on each end
of the lifting angles (Figure 4).
7. Attach lifting chains or cables to the clevis connectors. Each cable alone must be
strong enough to lift the chiller.
8. Attach cables to the lifting beam. Total lifting weight and centers of gravity are
listed in Table 5. Required lifting beam dimensions are shown in Figure 4. A rig-
ging diagram also ships with each unit. Lifting beam crossbars must be positioned
so lifting cables do not contact unit piping or control panel enclosure.
CAUTION
Unit Damage!
To prevent unit damage, position lifting beam crossbars so that cables
do not contact the unit.