48 RTAF-SVX001A-EN
Pre-Start
Upon completion of installation, complete the Sintesis™
RTAF Installation Completion Check Sheet and Request for
Trane Service checklist in chapter “Log and Check Sheets,”
p. 86.
Important: Start-up must be performed byTrane or an
agent ofTrane specifically authorized to
perform start-up and warranty ofTrane
products. Contractor shall provideTrane (or
an agent ofTrane specifically authorized to
perform start-up) with notice of the
scheduled start-up at least two weeks prior
to the scheduled start-up.