After installation
BMTK-SVN01D-EN 13
®
After installation
After installing the Tracker hardware, use the post-installation checklist
(Table 4) to verify that all installation procedures were completed.
Table 4. Tracker controller post-installation checklist
Inspect shipment upon receipt
_____ Verify that the shipment is complete.
_____ Inspect the controller and accessories to verify that
there has been no shipping damage or loss.
_____ File a damage claim with the carrier, if necessary.
_____ Verify that the controller received is the one that
was ordered.
_____ Write down the controller model number for use
later.
Verify termination module mounting
_____ Verify that the controller is in a safe indoor
environment.
_____ Verify that the location enables appropriate
personnel to access the controller.
_____ Verify that the controller is mounted securely with
recommended fasteners and screws.
_____ Verify that the installation conforms to controller
dimensions, recommended clearances, and
viewing angles.
Verify 24 Vac power wiring
_____ Verify that the power wiring complies with
applicable codes.
_____ Verify the 24 Vac power connection to the
controller termination Block TB1.
_____ Check the power wiring for shorts and improper
grounds.
_____ If using conduit connections, make sure separate
conduits are used for power and communications.
_____ Inspect the controller printed circuit card for
damage.
Verify input and output wiring
_____ Verify that wiring complies with specifications.
_____ Inspect all binary and analog terminations at TB1.
Verify communication wiring
_____ Verify that wiring complies with specifications.
_____ Inspect communication wiring between devices.
_____ Verify that all connections are properly shielded.
Verify wire terminations with a voltmeter
_____ Verify that the tests detailed in Table 18 on page 70
provide acceptable values.
Verify main module installation
_____ Verify that the main module is snapped in tightly
against the termination module.
_____ Verify that there is LED5 (HRT) activity.
Verify display module installation
_____ Verify that the display module is snapped in tightly
against the main module.
_____ Verify that the touch screen illuminates when
touched.
Verify direct and modem communication wiring
_____ Verify that the recommended cable is used for a
direct PC connection.
_____ Verify that the recommended adapter is used for
the direct connection cable.
_____ Verify that the direct connection cable is connected
to the correct Tracker port.
_____ Verify that the phone cable is connected to the
correct Tracker port.
Verify Ethernet communication wiring
_____ Verify that the recommended cable is used for the
connection.
_____ Verify that the Ethernet connection cable is
connected to the correct Tracker port.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane Tracker Version 12 and is the answer not in the manual?

Trane Tracker Version 12 Specifications

General IconGeneral
BrandTrane
ModelTracker Version 12
CategoryAir Conditioner
LanguageEnglish

Related product manuals