Leakage Test
If there are any doubts with insulation testing of the equipment, the standard (AS/NZ3760 since 2001) allows
for an alternative test method. A Leakage Test can be performed instead. (The TnP Prime is designed to
perform these tests).
NOTE: 10Amps MAXIMUM Resistive Load only (Standard TnP Prime).
A Leakage Test applies power to the Device Under Test (DUT) and measures the imbalance of leakage current
from the DUT between the active and neutral conductors. The leakage is tested to the limits specified in the
standard and a Pass/Fail result as well as a digital reading is provided to ensure that the user gains as much
information as necessary.
Earth Continuity Test - Commonly called Earth Bond Test
Note: Part of normal (Class 1 test) procedure. Use supplied IEC–Alligator Clip lead or optional accessory ‘WCM-Probe kit’.
The TnP Prime conducts earth continuity tests at Approx. 200mA. Continuity tests at higher currents are not
required or recommended on certain equipment as this may cause severe damage or premature failure to the
Device under test (see AS/NZS 3760:2010).
Unique Earth Bond Test Feature
The Earth Bond test duration can be controlled by the user by pushing the ENTER button during the test.
This will extent the test time by 30 seconds. The TnP Prime will then add 30 seconds to the test time for each
additional time you press ENTER. This feature has been incorporated to provide extra time to achieve an
adequate physical connection, or confirm any possible INTERMITTENT issues. There may be situations where
the condition of equipment, coatings applied, or suspect wiring breaks may alter the earth connection path of
the device under test. This may save time by prolonging tests instead of conducting multiple iterations of the
same test.
3 Phase Testing
Note: 3 Phase Testing requires a three phase adaptor, sold separately. The TnP Prime cannot perform a 3 Phase Leakage
test.
3 Phase appliances can be tested by the TnP Prime appliance testers. As the insulation tests are from Phase to
Earth, only a 500V insulation test is required. This test may be carried out by using the optional adaptor ‘WCM-
3PH-MADP’ [See ‘Optional Accessories’ for details.]
To change the test voltages, when in Main Menu A; Press Enter and F2 together to enter in settings. Select
“Change Insulation Vol” and press enter. Select either 250V or 500V. TnP Prime defaults to 500VDC, and will
revert back to that when restarted.
Integrated Tests
Mains Supply Test
Note: The Mains Supply Test only applies when connected to Mains Power - if you are using your TnP Prime in battery
mode, you can disregard this.

Other manuals for Wavecom TnP Prime

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wavecom TnP Prime and is the answer not in the manual?

Wavecom TnP Prime Specifications

General IconGeneral
BrandWavecom
ModelTnP Prime
CategoryTest Equipment
LanguageEnglish

Related product manuals