3.3.4 Program sequence
Pre-purge
At heat demand, the burner motor starts after the initialisation time(TI) has elapsed
and the gas pressure switch has been activated.
The air pressure switch is activated during the pre-purge phase (TV).
Ignition
Pre-ignition time(TVZ) starts before the end of the pre-purge time (TV).
Ignition starts.
Fuel release
Following pre-ignition time(TVZ) the double gas valve(K32) opens and releases the
fuel.
Safety time
With fuel release, safety time (TS) and post-ignition time (TNZ) start.
The flame signal must be present within the safety time (TS).
Operation
The combustion manager monitors the flame signal via the ionisation electrode.
Post-purge
If there is no longer a heat demand, the double gas valve(K32) closes and stops
the fuel supply.
Post-purge time(TN) begins.
Following the post-purge time(TN) the burner motor switches off.