7 Commissioning
83240802 1/2020-01 La
46-96
7.4 Concluding work
Check control and safety devices.
Remove gas pressure measuring devices and close all test points.
Conclude valve proving of gas valve train (fourth test phase) [ch.7.1.3].
Enter combustion values and settings in the commissioning record and/or test
sheet.
Mount cover on burner.
Inform the operator about the use of the equipment.
Hand the installation and operating manual to the operator and inform him that
this should be kept with the appliance.
Point out to operator that the installation should be serviced annually.