Procedure
1. Make sure that the crane and the soft lifting slings are approved for the total weight of the transport
box and bushing. Refer to the weight in the packing list.
2.
Attach soft lifting slings (8).
3.
Make sure that the angle of the soft lifting sling is not more than 20°.
4.
Carefully lift the transport box.
5.
Set down the transport box on a flat surface.
End of instruction
3.4.2 Lifting the bushing out of the transport box
Overview
G005004
79 Top end nut
Procedure
1. Make sure that the crane is approved for lifting the weight of the bushing. Refer to the net weight on
the packing list.
2.
Open the transport box.
NOTE!
The cover is attached with bolts.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB GOE Series and is the answer not in the manual?

ABB GOE Series Specifications

General IconGeneral
BrandABB
ModelGOE Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals