Operation Manual / TPL67-C.. - TPL71-C..
Page 36
© Copyright 2016 ABB. All
rights reserved.
April 2016 HZTL2488_EN Revision C
3.2
Inspection work includes preventive visual controls plus monitoring and
measuring work before and during commissioning. Inspections help detect
changes to the turbocharger. Machine damage can be avoided.
Inspection before commissioning
Check for correct functioning.
Inspect for damage.
Check oil filter for cleanliness before commissioning.
Particles of dirt and solid matter in the oil can cause serious damage to
the machine or property.
During initial commissioning and after all service work, the complete
lubricating system must be flushed thoroughly with warm oil.
When running in the engine and after all service work on the lubricat-
ing system, special running-in filters must be used.
Check oil pressure in oil supply lines.
Check whether the warning plates are present and legible.
Check whether the protective sheets have been removed.
Warning plates on tur-
bocharger