Commissioning
3
Inspection work
3.2
Page 36
© Copyright 2017 ABB. All rights reserved.
February 2017 HZTL2488_EN Revision D
Inspection work
3.2
Inspection work includes preventive visual controls plus monitoring and
measuring work before and during commissioning. Inspections help detect
changes to the turbocharger. Machine damage can be avoided.
Inspection before commissioning
Check for correct functioning.
Inspect for damage.
Check oil filter for cleanliness before commissioning.
CAUTION
Contaminated oil
Particles of dirt and solid matter in the oil can cause serious damage to
the machine or property.
During initial commissioning and after all service work, the complete
lubricating system must be flushed thoroughly with warm oil.
When running in the engine and after all service work on the lubricat-
ing system, special running-in filters must be used.
Check oil pressure in oil supply lines.
CAUTION
Prelubrication
Serious machine or property damage might result if the turbocharger is
not supplied with oil when the engine is starting.
Activate prelubrication device before starting engine.
Check whether the warning plates are present and legible.
Check whether the protective sheets have been removed.
3.2
3.2.1
Monitoring devices
Filter mat
Lubricating system
Warning plates on
turbocharger

Table of Contents

Other manuals for ABB TPL67-C Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TPL67-C Series and is the answer not in the manual?

ABB TPL67-C Series Specifications

General IconGeneral
BrandABB
ModelTPL67-C Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals