The grease of the bearings has to be changed once a year for an operating
time higher than 5000 h per year or every 5000 hours for an operating time
lower than 5000 h/year.
Clean the bearings before regreasing.
5.3. Motor installation (if applicable)
It is possible to install any type of electric or hydraulic motor of which the
specifications comply to the technical data, with flange and shaft corresponding
to:
M112 – B14 (FT130) size as per standard IEC600721 (for Europe and Wide
motor versions) and motor frame size 213 with 184 TCH flange for NEMA
motor version for GVS 100A
M112 – B5 (FF215) size as per standard IEC600721 (for Europe and Wide
motor versions) and motor frame size 213 TC for NEMA motor version for
GVS 200A
M132 – B14 (FT215) size as per standard IEC600721 (for Europe and Wide
motor versions) and motor frame size 256 TC with 215 TC flange for Nema
motor version for GVS 300A
Motor installation instructions
1. Remove the fixing clamp from the connecting joint on the pump.
2. Install the assembly on the motor shaft taking into account the stated
measure.
3. T
ighten the screw to firmly fix the assembly to the shaft.
Installation
12/2021 - ©Atlas CopcoPage 586996022430_C

Other manuals for Atlas Copco GVS 100A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Atlas Copco GVS 100A and is the answer not in the manual?

Atlas Copco GVS 100A Specifications

General IconGeneral
BrandAtlas Copco
ModelGVS 100A
CategoryWater Pump
LanguageEnglish

Related product manuals