EasyManuals Logo
Home>Furuno>Marine Radar>FELCOM 15

Furuno FELCOM 15 Service Manual

Furuno FELCOM 15
228 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #77 background imageLoading...
Page #77 background image
5.1 PV (Performance Verification) test
5-1
5.1 PV (Performance Verification) test
PV test is for checking the MES function. The signal (message) is exchanged between
MES and LES.
5.1.1 PV test sequence
1. Select PV test on the Test menu.
2. The MES requests NCS to conduct PV test.
3. The NCS acknowledges request for testing.
4. The MES, upon receiving acknowledgement from NCS, goes into pending state.
5. NCS select a (not busy) LES to perform the test.
6. The LES transmits a test message to the MES.
7. The MES transmits the test message to the designated LES.
8. Distress alert testing. The MES transmits the distress alert transmission test.
The distress alert is automatically transmitted within two minutes.
9.
When the distress alert test is finished the results of the PV test are sent to MES.
Cha
p
ter 5. Maintenance

Table of Contents

Other manuals for Furuno FELCOM 15

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Furuno FELCOM 15 and is the answer not in the manual?

Furuno FELCOM 15 Specifications

General IconGeneral
BrandFuruno
ModelFELCOM 15
CategoryMarine Radar
LanguageEnglish

Related product manuals