www.gemu-group.com18 / 24GEMÜ 8500
13 Commissioning
13 Commissioning
CAUTION
Protect against leakage!
● Check the tightness of the media con-
nections prior to commissioning!
● Provide precautionary measures
against exceeding the maximum per-
mitted pressures caused by pressure
surges.
Prior to cleaning or commissioning the plant:
1. Check the tightness and the function of the pilot solenoid
valve.
2. If the plant is new or repair work has just taken place, blow
out the piping system with a fully opened pilot solenoid
valve (to remove any harmful foreign matter).
Cleaning
• The plant operator is responsible for selecting the cleaning
medium and performing the procedure.