User Manual V1.0-2022-01-17
09 Maintenance
9.5 Routine Maintenance
Maintaining Item Maintaining Method Maintaining Period
System Clean
Check the heat sink, air intake, and air
outlet for foreign matter or dust.
Once 6-12 months
Fan
Check the fan for proper working status,
low noise, and intact appearance.
Once a year
DC Switch
Turn the DC switch on and o󽗈 ten
consecutive times to make sure that it is
working properly.
Once a year
Electrical
Connection
Check whether the cables are securely
connected. Check whether the cables are
broken, or whether there is any exposed
copper core.
Once 6-12 months
Sealing
Check whether all the terminals and ports
are properly sealed. Reseal the cable hole
if it is not sealed or too big.
Once a year
THDi Test
For Australia requirements, in the THDi
test, there should add Zref between
inverter and mains.
Zref:
Zmax or Zref (phase current>16A)
Zref: L: 0.24 Ω + j0.15 Ω; N: 0.16 Ω + j0.10 Ω
(phase current>16A, <21.7A)
Zref: L: 0.15 Ω + j0.15 Ω; N: 0.1 Ω + j0.1 Ω
(phase current>21.7A, <75A)
Zref: ≥5% Un/Irated+j5% Un/Irated (phase
current>75A)
As needed

Other manuals for Goodwe SDT G2 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Goodwe SDT G2 Series and is the answer not in the manual?

Goodwe SDT G2 Series Specifications

General IconGeneral
BrandGoodwe
ModelSDT G2 Series
CategoryInverter
LanguageEnglish

Related product manuals