Figure 5 Hoisting the RRU onto the tower
(1) Lifting sling
(2) Fixed pulley
(3) Traction sling
NOTICE:
The load-bearing capacity of each sling must be greater than 200 kg (441 lb) and the
diameter of each sling must be less than 25 mm (0.98 in.).
When hoisting each device onto a tower, protect them from colliding with the tower.
Hoist the RRU onto the tower before it is installed on a pole, angle steel, or U-steel.
Do not hoist anything using the traction eye.
7. Installation engineer A catches the RRU hoisted onto the tower.
8. Installation engineer A installs the RRU onto the main bracket and uses an inner hexagon torque
screwdriver to tighten the captive screw into the hole of the attachment plate and main bracket
to 5 N·m (44.25 lbf·in.). For detailed operations, see steps 4 and 5 in Installing a Single RRU.
9. Untie the lifting sling and traction sling.
NOTE:
The procedure for hoisting the RRU and its mounting kits onto the tower is for your reference only.
Parent Topic: Hoisting an RRU and Related Cables onto a Tower
Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei RRU5309w and is the answer not in the manual?

Huawei RRU5309w Specifications

General IconGeneral
BrandHuawei
ModelRRU5309w
CategoryConference System
LanguageEnglish

Related product manuals