Start−Up & Performance Check List
Gas Supply Pressure
SUPPLY
AIR
Line Voltage
GAS SUPPLY
Natural Gas
LP Propane Gas
Piping Connections Tight
Leak Tested
Supply Line Pressure W.C.________
1
INTAKE / EXHAUST PIPE
All Joints Primed and Glued
Terminations Installed Properly
Pipes Supported
Condensate Trap Primed / Line Sloped
Heat Cable Installed and Operable (if applicable)
2
2
2
1
Horizontal Pipes Sloped (if applicable)
UNIT SET UP
3
4
5
Flter
RETURN AIR
1
Furnace:
Model Number_______________
Serial Number_________________
3
DUCT SYSTEM
SUPPLY AIR DUCT
Sealed
Insulated (if necessary)
RETURN DUCT
Sealed
Filter Installed and Clean
Grilles Unobstructed
4
5
CONTROL BOARD
DIP Switches Set
Appropriate Links in Place
VOLTAGE CHECK
Supply Voltage _____
Electrical Connections Tight

Other manuals for Lennox G43UF

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lennox G43UF and is the answer not in the manual?

Lennox G43UF Specifications

General IconGeneral
BrandLennox
ModelG43UF
CategoryFurnace
LanguageEnglish

Related product manuals