21
e condensate trap is built into the boiler, an external trap is
not required and should NOT be used.
Provide ½” PVC condensate drain and ttings. Condensate
drain to be pitched down to oor drain at a minimum of ¼”
per foot.
Install furnished ½” PVC tee to overow tting as shown in
Figure #8.
e ½” diameter schedule 40 PVC or CPVC condensate drain
and pipe ttings must conform to ANSI standards and ASTM
D 1785 or D2846. Schedule 40 PVC or CPVC cement and
primer must conform to ASTM D2564 or F493. In Canada,
use CSA or ULC certied schedule 40 PVC or CPVC drain
pipe cement.
A condensate pump with a reservoir (not furnished) may be
used to remove condensate to a drain line (sanitary line) above
boiler if a oor drain is not available or its in accessible.