–74–
Freeze Sequence
3. Prechill
The compressor is on for 30 seconds prior to water
flow to prechill the evaporator. The water fill valve
remains on until the water level probe is satisfied.
4. Freeze
The water pump restarts after the 30-second prechill.
An even flow of water is directed across the
evaporator and into each cube cell, where it freezes.
The water fill valve will cycle on, then off one more
time to refill the water trough.
When sufficient ice has formed, the water flow (not the
ice) contacts the ice thickness probe. After
approximately 7 seconds of continual water contact,
the Harvest sequence is initiated. The ice machine
cannot initiate a Harvest sequence until a 6-minute
freeze lock has been surpassed.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc CVD2075 and is the answer not in the manual?

Manitowoc CVD2075 Specifications

General IconGeneral
BrandManitowoc
ModelCVD2075
CategoryIce Maker
LanguageEnglish

Related product manuals