EasyManuals Logo
Home>Trane>Chiller>RTAA-110

Trane RTAA-110 User Manual

Trane RTAA-110
178 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #47 background imageLoading...
Page #47 background image
RTAA-SVX01A-EN 47
Installation — Remote Evaporator
Oil Charge Determination
The unit is factory charged with the amount of oil required by the system,
without the field-installed piping. The amount of additional oil required is
dependent upon the amount of refrigerant that is added to the system for the
field-installed piping.
Use the following formula to calculate the amount of oil to be added:
Pints of Oil (Trane Oil-31) =
lbs of refrigerant added for field-installed piping
100
From the example above, in which the weight of the additional refrigerant
added for the field-installed piping was 34.0 lbs (30.6 + 3.4), the amount of oil
to be added equals 0.34 pints (34.0/100) per circuit.
Example: Refrigerant Charge Computation
Determine the approximate amount of charge required for an RTAA 100 ton
unit with a remote evaporator that is located 75 feet away (i.e the actual
length of field-installed pipe is 75 feet for each suction line and liquid line).
Assume that the suction lines have been previously determined to be in.,
O.D. and the liquid lines are in. 1-1/8 O.D.
Relief Valve Venting
All relief valve venting is the responsibility of the installing contractor.
The remote evaporators on chillers sold with this option utilize relief valves
installed in each circuit of the evaporator head. There is one relief valve per
circuit, and they must be vented to the outside of the building.
1. From Table 2g for a 50 ton
circuit requires:
= 73 lbs. R-22
2. From Table 2h for a 2-518
inch OD suction line:
75 feet x 4.5 feet = 3.4 lbs. R-22
3. From Table 2h for a 1 118
inch OD liquid line:
75 feet x 40.8 feet = 30.6 Ibs. R-22
4. Total R-22 charge per circuit: Sum results of steps
1,2, and 3
= 107 Ibs. R-22 per circuit
5. Total R-22 charge per machine: 2 circuits x 107 Ibs. = 214 Ibs. R-22 per machine
Table 9 Field-Installed Piping Charge
Lbs. R-22 per 100 ft.
Pipe O.D.
(inches) Suction Line Liquid Line
1-1/8 0.78 40.8
1-3/8 1.2 62.2
1-5/8 1.7 88
2-1/8 2.9 153.1
2-5/8 4.5 236.1
3-1/8 6.4

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane RTAA-110 and is the answer not in the manual?

Trane RTAA-110 Specifications

General IconGeneral
BrandTrane
ModelRTAA-110
CategoryChiller
LanguageEnglish

Related product manuals