Mechanical installation 29
Mechanical installation
Contents of this chapter
This chapter describes the mechanical installation of the inverter. Obey all local
regulations.
Safety
Refer to Safety instructions on page 9.
For instructions on how to move the inverter, refer to Storing, lifting and transporting on
page 23.
Required tools
The tools required to move the inverter, fasten it to the foundation and tighten the
connections:
• Crane, fork-lift or pallet truck (with sufficient load capacity), and iron bar, jack and
rollers.
• Pozidriv and Torx (2.5...6 mm) screwdrivers
• Torque wrench
• Set of wrenches and sockets
Unpacking
Before the delivery check and the installation, unpack the inverter from the transportation
and storage package. Be careful to not cause damage to the inverter.
To prevent damage to the inverter, unpack the inverter as late as possible before the
installation.