Eaton's Service Information MN280043EN provides
assembly and installation instructions for its Cooper
Power™ series KNOVA59-1 and KNOVA59-3 substation
frames. It contains a convenient step-by-step explanation
of installation procedures as well as a parts list. Before
assembling the frame, carefully read and understand the
contents of this manual.
Read this manual first
Read and understand the contents of this manual and follow
all locally approved procedures and safety practices before
installing or operating this equipment.
Additional information
These instructions cannot cover all details or vari ations
in the equipment, procedures, or process described nor
provide directions for meeting every possible contin gency
during installation, operation, or maintenance. For additional
information, please contact your Eaton representative.
Acceptance and initial inspection
All frame parts are inspected at the factory. They are in good
condition when accepted by the carrier for shipment.
Upon receipt, inspect the shipping container for signs
of damage. Unpack and inspect thoroughly for damage
incurred during shipment. If damage is discovered, file a
claim with the carrier immediately.
Handling and storage
Be careful during handling and storage of the frame to mini-
mize the possibility of damage. If the frame is to be stored
for any length of time prior to assembly or installation,
provide a clean, dry storage area.
Quality standards
ISO 9001 Certified Quality Management System
Description of frame
The substation frame referenced in these instructions is
intended for the following switchgear:
•
NOVA
®
Three-Phase, Microprocessor-Controlled Recloser
•
DAS Three-Phase, Vacuum-Break Distribution Automation
Switch
•
VCS-3 Three-Phase, Vacuum-Break Capacitor Switch
•
TVS Time-Voltage Sectionalizer
•
NOVA STS Three-Phase, Microprocessor-Controlled
Recloser
The galvanized frame is constructed of rigid structural or
formed steel. The hardware is stainless steel. Practical,
welded construction is used to provide a high degree of
rigidity with minimum weight. The substation frame height
is adjustable to satisfy a variety of application conditions.