Eaton 93E UPS 15-80 kVA (380/400/415 V) Installation and Operation Manual
© Eaton Corporation plc 2015. All rights reserved. Revision: 001
Document ID: 614-01975-00
51 (133)
3.
Remove the 4 bolts that secure
the front shipping bracket to
the cabinet and the 4 bolts that
secure the bracket to the pallet.
If you are not installing the
cabinet permanently, retain the
shipping bracket and securing
hardware for later use.
4.
If the levelling feet are not fully
retracted, turn the levelling feet
until they are retracted.
5.
Remove the 4 bolts that secure the rear shipping bracket to the
cabinet and the 4 bolts that secure the bracket to the pallet. If you
are not instal
ling the cabinet permanently, retain the shipping bracket
and securing hardware for later use.
WARNING
Do not stand directly in front of the pallet while unloading the cabinet.
If unloading instructions are not closely followed, the cabinet may
cause serious injury.
6.
Slowly roll the cabinet toward
the front of the pallet. Continue
rolling the cabinet down the
ramp until the cabinet is clear of
the ramp.
7.
Roll the cabinet to its final installation location.
8.
If you are not installing the cabinet permanently, retain the shipping
brackets and hardware. Otherwise, recycle the pallet, ramp, and
shipping brackets in a responsible manner.

Table of Contents

Other manuals for Eaton 93P

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Eaton 93P and is the answer not in the manual?

Eaton 93P Specifications

General IconGeneral
BrandEaton
Model93P
CategoryUPS
LanguageEnglish

Related product manuals