2 Planning
2.1 Installation checklist
□ Verify the contents of the product shipment to confirm that you have all parts and
information necessary for the installation.
□ Verify that the meter calibration-type code corresponds to the pipe size. If it does not,
measurement accuracy may be reduced due to the boundary effect.
□ Make sure that all electrical safety requirements are met for the environment in which
the meter will be installed.
□ Make sure that the local ambient and process temperatures and process pressure are
within the limits of the meter.
□ Make sure that the hazardous area specified on the approval tag is suitable for the
environment in which the meter will be installed.
□ Make sure that you will have adequate access to the meter for verification and
maintenance.
□ Verify that you have all equipment necessary for your installation. Depending on your
application, you may be required to install additional parts for optimal performance of
the meter.
□ If your meter will be wired to a remote-mount 2700 FOUNDATION
™
Fieldbus transmitter:
— Refer to the instructions in this manual for preparing the 4-wire cable and wiring to
the processor connections.
— Refer to the instructions in the transmitter installation manual for mounting and
wiring the 2700 fieldbus transmitter.
— Consider the maximum cable length between the meter and transmitter. The
maximum recommended distance between the two devices is 1,000 ft (305 m).
Use Micro Motion cable.
Installation Manual Planning
MMI-20020989 May 2019
Installation Manual 7