Setup reminders
Venue 50 – Basic Service Manual 3-3
5447566-100 English Rev. 7
Setup reminders
Average setup time
• Unpacking the Venue 50: 20 minutes
• Set up Venue 50 wo/options: 30 minutes (dependent on the
configuration that is required)
• DICOM Network Configuration: 30 minutes
The Venue 50 installation and functional checkout will take
approximately one hour. Venue 50 console with optional
equipment may take slightly longer.
Setup warnings
WHEN USING ANY TEST INSTRUMENT THAT IS CAPABLE
OF OPENING THE AC GROUND LINE (I.E., METER’S
GROUND SWITCH IS OPEN), DON’T TOUCH THE
ULTRASOUND SYSTEM!
To prevent electrical shock, connect the unit to a properly
grounded power outlet. Do not use a three to two prong
adapter. This defeats safety grounding.
Do not wear the ESD wrist strap when you work on live circuits
and more than 30 V peak is present.
Do not operate this unit unless all board covers and frame
panels are securely in place. System performance and cooling
require this.