EasyManuals Logo

IDEAL Mexico RS 3/100 User Manual

IDEAL Mexico RS 3/100
36 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #14 background imageLoading...
Page #14 background image
14
Mexico Super RS 3/100 & 3/125 - Installation
INSTALLATLON
10
GAS CONNECTION
INSTALLATION
1. Open vent and cold feed connections must be made
to the boiler flow and return tappings according to
the options shown in Frame 6.
2. The boiler is assumed to be the highest point of the
circulating system.
3. The circulating pump is positioned on the FLOW
and the vertical distance, between the pump and
feed/ expansion tank, must comply with the pump
manufacturer's minimum requirements, to avoid
cavitation. Should these conditions not apply, either
lower the pump position or raise the feed/ expansion
tank above the minimum requirements of Caradon
Plumbing Limited.
4. The water velocity through the boiler flow / return
pipes is assumed to be below 1 m/s (3 ft./s), whilst
the pump flow rate is set to provide a temperature
difference of 11
o
C (20
o
F) across the boiler flow /
return, at design input.
5. This information is intended as a GUlDE ONLY and
cannot take into account instantaneous changes in
head caused by the operation of motorised valves,
pumps etc.
Due allowance MUST be made if surging is liable to
occur.
If in any doubt, contact Caradon Plumbing Ltd.
Boiler Dimension A
RS 3/100 473 (8 5/8")
RS 3/125 546 (21 1/2")
12
MINIMUM REQUIREMENTS Fully pumped systems
1. A MINIMUM working gas pressure of
20 mbar (8 in.w.g.) MUST be available
at the boiler inlet, with the boiler
operating.
2. Extend a gas supply pipe NOT LESS
THAN 15mm (
1/2") OD to the boiler and
connect to the gas cock situated at the
front LH side of the boiler.
3. Test the gas installation for soundness
and purge in accordance with BS.6891:
1988. Refer to Frame 24.
11
WATER CONNECTIONS
1. Connect the system flow and return pipework to the boiler
as appropriate. Refer to Frames 12 and 13 for guidance on
system design.
Note. When the required output exceeds 14.4 kW (49 000
Btu/h) then 28mm (1") pumped flow and return pipes
should be used, both to and from the boiler.
Gravity connections MUST be at least 28mm (1").
2. Ensure that all valves are open. Fill and vent the system
and check for water soundness.
Notes.
a. Isolating valves must be fitted as close to the pump as
possible.
b. The boiler is not suitable for use with a direct hot water
cylinder.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL Mexico RS 3/100 and is the answer not in the manual?

IDEAL Mexico RS 3/100 Specifications

General IconGeneral
BrandIDEAL
ModelMexico RS 3/100
CategoryBoiler
LanguageEnglish

Related product manuals