Inspection of the installation
Current regulations require the heating installation to be inspected before it is commissioned. The inspection must
be carried out by a suitably qualified person.
In addition, fill in the page for the installation data in the User Manual.
DateSignatureNotesDescription
Brine (page 16)
System flushed
System vented
Antifreeze
Level/Expansion vessel
Filterball (particle filter)
Safety valve
Shut off valves
Circulation pump setting
Heating medium (page 17)
System flushed
System vented
Expansion vessel
Filterball (particle filter)
Safety valve
Shut off valves
Circulation pump setting
Electricity (page 20)
Connections
Main voltage
Phase voltage
Fuses heat pump
Fuses property
Outside sensor
Room sensor
Safety breaker
Earth circuit-breaker
Setting of emergency mode thermostat
Miscellaneous
Warranty
Benchmark checklist