8 - 7
Installation and commissioning
8.03 Commissioning
● Check the machine, particularly its electrical wiring and pneumatic tube connections, for
any damage.
● Clean the machine thoroughly and afterwards fill with oil and oil the machine (see Chap-
ter 10, Care and maintenance).
● Have a mechanic check whether the motor of the machine can be used with the avail-
able power supply and that the motor is correctly connected in the junction box.
Do not operate the machine if there is any discrepancy.
● When the machine is running, the balance wheel must turn towards the operator. If it
does not, have the motor connection changed by a mechanic.
● Connect the machine to the compressed air supply. When it is connected, the gauge
should indicate a pressure of approx. 6 bar. If necessary have this reading correctly set
(see Chapter 10.03, Checking/adjusting the air pressure).
● Before commissioning the machine, remove grommet 1 of oil container 2.
Grommet 1 is only needed for
support during transportation
and must not be used while the
machine is in operation.
12
Fig. 8 - 08
8.04 Switching the machine on/off
● Switch the machine on (see Chapter 7.01, On/off switch).
● Carry out a running test.