Acquisition
Acquisition
This section contains concepts of and procedures for using the acquisition system.
Signal path compensation
Use this procedure if the temperature has changed more than 5 °C (9 °F) since the last signal path compensation (SPC).
Perform the s
ignal path compensation regularly to ensure that your measurements have the highest level of accuracy.
Tektronix considers it a best practice to run SPC when using the instrument to measure signals with higher sensitivity
(10 mV/div and lower) settings regardless of temperature shift or time since it was last run. Failure to do so may result in
the instrum
ent not meeting warranted performance levels.
1. Prerequisi
tes: instrument powered on
for 20 minutes, and all input signals
removed.
2. Select In stru men t Calibration.
3. When the Temperature Status changes
to Rea
dy, click Run SPC to start the
calibration. Calibration may take 10 to
15 minutes.
MSO/DPO70000DX, MSO/DPO70000C, DP O7000C, and MS O/DPO5000 Series U ser M anual 31

Table of Contents

Other manuals for Tektronix DPO5000 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Tektronix DPO5000 Series and is the answer not in the manual?

Tektronix DPO5000 Series Specifications

General IconGeneral
BrandTektronix
ModelDPO5000 Series
CategoryTest Equipment
LanguageEnglish

Related product manuals