EasyManuals Logo
Home>Trane>Chiller>Sintesis RTAF HE series

Trane Sintesis RTAF HE series User Manual

Trane Sintesis RTAF HE series
176 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #6 background imageLoading...
Page #6 background image
RLC-SVX19G-GB
6
4 UNT-PRC002-GB
Technical Data
FWD 08 12 20 30 45
Power supply (V/Ph/Hz) 230/1/50
Capacities
Cooling capacity on water (1) (kW) 5,2 8,3 15 18,8 30,1
Heating capacity on water (2) (kW) 6,3 11,9 18,9 20,9 38,2
Fan motor (type) 2 x direct drive centrifugal
Fan power input (3) (kW) 0,23 0,46 0,65 1,04 1,51
Current amps (3) (A) 1,1 2,2 3,1 4,7 5,5
Start-up amps (A) 3,2 5,5 9,3 14,1 16,5
Air flow
minimum (m
3
/h) 490 980 1400 1800 2700
nominal (m
3
/h) 820 1650 2300 3000 4500
maximum (m
3
/h) 980 1970 2600 3600 5400
Main coil
Water entering/leaving connections (type) ISO R7 rotating female
(Dia) 3/4" 3/4" 1 1/2" 1 1/2" 1 1/2"
Electric heater (accessory for blower only)
Electric power supply (V/Ph/Hz) 230/1/50 230/1/50 or 400/3/50 400/3/50 400/3/50 400/3/50
Heating capacity (kW) 2/4 8 10 12 12
Hot water coil (accessory for blower only)
Heating capacity (4) (kW) 6,3 12 17,4 22,4 34,5
G2 filter (filter box accessory)
Quantity 2 2 2 2 2
Dimensions ( LxWxth) (mm) 386x221x8 486x271x8 586x321x8 586*421*8 586*621*8
G4 filter (filter box accessory)
Quantity - 2 2 2 2
Dimensions ( LxWxth) (mm) - 486x264x48 586x314x48 586*414*48 586*614*48
Condensate pump (accessory) (type) Centrifugal
Water flow - lift height (l/h - mm) 24 - 500
Not available for FWD30 and FWD45
Sound level (L/M/H speed)
Sound pressure level (5) (dB(A)) 36/40/43 38/41/44 46/50/53 47/52/57 47/52/58
Sound power level (5) (dB(A)) 46/50/53 48/51/54 56/60/63 57/62/67 57/62/68
Unit dimensions
Width x Depth (mm) 890 x 600 1090 x 710 1290 x 820 1290 x 970 1290 x 1090
Height (mm) 250 300 350 450 650
Shipped unit dimensions
Width x Depth (mm) 933 x 644 1133 x 754 1333 x 864 1333 x 1008 1333*1133
Height (mm) 260 310 360 460 660
Weight (kg) 32 46 61 76 118
Colour galvanised steel
Recommended fuse size
Unit alone (aM/gI) (A) 8/16 8/16 8/16 8/25 8/25
Unit with electric heater (gI) (A) 16 (2kW),25 (4kW) 40 (230V),3*16 (400V) 3*20 3*25 3*25
(1) Conditions: Water entering/leaving temperature: 7/12 °C, Air inlet temperature 27/19°C DB/WB - Nominal air flow
(2) Conditions: Water entering/leaving temperature: 50/45 °C, Air inlet temperature 20°C DB - Nominal air flow
(3) At high speed with nominal air flow.
(4) Water entering/leaving temperature 90/70 °C, air inlet temperature 20 °C DB, Nominal air flow.
(5) A rectangular glass wool duct 1m50 long is placed on the blower.The measurement is taken in the room containing the blower unit.
Heat exchanger operating limits:
FWD:
*water temperature: max 100° C
*absolute service pressure: min 1 bar/max 11 bars
Accessories - Hot water coil:
*water temperature: min. +2° C/max. 100° C
*absolute service pressure: min 1 bar/max 11 bars
Pre-Installation
Installation Requirements
A list of the contractor responsibilities typically associated with the unit installation process is provided in Table 1.
Table 1
Installation requirements
Type
Trane Supplied
Trane Installed
Trane Supplied
Field Installed
Field Supplied
Field Installed
Foundation Meet foundation requirements
Rigging
Safety chains
Clevis connectors
Lifting beam
Spreader bar
Isolation
Elastomeric
isolators
(optional)
Elastomeric isolators (optional)
Electrical
Circuit breakers
(optional)
Unit mounted
starter
Circuit breakers (optional)
Electrical connections to unit mounted starter
Wiring sizes per submittal and NEC
Terminal lugs
Ground connection(s)
BAS wiring (optional)
Control voltage wiring
Chilled water pump contactor and wiring
Option relays and wiring
Water piping Flow switch
Taps for thermometers and gauges
Thermometers
Water ow pressure gauges
Isolation and balancing valves in water piping
Vents and drain
Waterside pressure relief valves
Water strainer
Insulation Insulation Insulation
Water Piping Connection Components Grooved pipe
Other Materials
R-134a, R-513A
or R1234ze
refrigerant
Full factory
charge or pre-
load charge
Dry nitrogen
(optional)
Glycol for Glycol free conguration
“Sintesis Model RTAF Installation
Completion Check Sheet and Request
for Trane Service”
Chiller Start-up Commissioning
(a)
Trane, or an
agent of Trane
specically
authorized to
perform start-
up of Trane
®
products
(a)
Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up and warranty of Trane® products. Contractor
shall provide Trane (or an agent of Trane specifically authorized to perform start-up) with notice of the scheduled start-up at least two weeks prior to the
scheduled start-up.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane Sintesis RTAF HE series and is the answer not in the manual?

Trane Sintesis RTAF HE series Specifications

General IconGeneral
BrandTrane
ModelSintesis RTAF HE series
CategoryChiller
LanguageEnglish

Related product manuals