Appendix 2 Installation Instruction Of Battery Rack 25
NetSure 531 A41, NetSure 531 A91 Subrack Power system User Manual
2. Installation Instruction Of Three-Layer Battery Rack
Packing list
Accessory 1 Accessory 2 Accessory 3 Accessory 4
Figure 5 Accessory
Table 3 Packing list of the battery rack
Accessory
Accessory number
Accessory 1
2
Accessory 2
6
Accessory 3
3
Accessory 4
2
Expansion bolt
4 pieces
Fastener
1 set
Installation procedures
1. Install accessory 1 and accessory 2 according to Figure 6 (a).
2. Install accessory 3 according to Figure 6 (b).
Accessory 1
Accessory 2
Accessory 3
(a) (b)
Figure 6 Installation procedure of accessory 1 ~ accessory 3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv NetSure 531 A91 and is the answer not in the manual?

Vertiv NetSure 531 A91 Specifications

General IconGeneral
BrandVertiv
ModelNetSure 531 A91
CategoryPower Supply
LanguageEnglish

Related product manuals