08 COMMISSIONING
3BHS213401 E01 REV H ACS1000 AIR-COOLED USER MANUAL 110/184
8.2 Commissioning checklist
This checklist is designed to help you prepare the drive and associated equipment
for commissioning.
8.2.1 Mechanical installation checklist
8.2.2 Electrical installation checklist
1.
Drive installed according to the instructions in this user manual
(3BHS213401 E01 Rev H).
□
2.
Drive securely fastened to the floor (if applicable)
□
3.
Redundant fan unit installed (if applicable)
□
4.
Visual inspection:
- No badly affixed or damaged components
- No foreign objects inside cabinet
- No dirt, dust and humidity inside cabinet
□
1.
Types and cross sections of control cables suitable for the signal type and
signal level
□
2.
Types and cross sections of power cables selected according to the instructions
in this user manual (3BHS213401 E01 Rev H).
□
3.
Pulse encoder connected according to the relevant manual (only applicable for
drives with pulse encoder interface)
□
4.
Cable entry prepared according to the instructions in this user manual
(3BHS213401 E01 Rev H).
□
5.
All control cable screens and conductors are connected according to the
instructions of the user manual, appropriately labeled, and the customer-side
connections are completed
□
6.
Equipotential bonding conductor of drive securely connected at both ends
□
7.
Converter transformer and motor cables not connected at both ends (cables
and drive must be insulation resistance tested (Megger test) before connection)
□