ABB i-bus
®
KNX
Commissioning
FCA/S 1.x.x.1 | 2CDC508134D0202 151
Function Time on OFF
Options:
None
Switching delay
Minimum time
This defines the Time function on Fan OFF.
None: No Time function is executed.
Switching delay: The fan is switched off after this delay.
Minimum time: The fan remains OFF for at least this time.
Selection of option Switching delay:
Dependent parameter:
Time in s [1…65,535 x 0.1]
Options:
1…20…65,535
The fan is switched off after this delay.
Selection of option Minimum time:
Dependent parameter:
Time in s [1…65,535]
Options:
1…20…65,535
The fan remains OFF for at least this time.
Enable communication object
"Forced operation" 1-bit
Options:
No
Yes
Yes: A 1 bit Forced operation communication object is enabled.
Dependent parameters:
Forced operation on object value
Options:
0
1
0: Forced operation is activated by a telegram with value 0.
1: Forced operation is activated by a telegram with value 1.
Reaction on forced operation
Options:
Unchanged
OFF
ON
This parameter defines how the fan should respond to a forced operation.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB i-bus EIB and is the answer not in the manual?

ABB i-bus EIB Specifications

General IconGeneral
BrandABB
Modeli-bus EIB
CategoryController
LanguageEnglish

Related product manuals