33.
Commissioning
Mechanical
The following mechanical commissioning instructions are for liquid fuel pumps and dispensers.
If LPG, CNG, or AdBlue is being dispensed, refer to the specific manuals for these.
Make sure that the electrical commissioning tests have been carried out and the solenoid
operation has been verified before carrying out the following tests.
Ensure the power supply to the dispenser is turned on, and lift the nozzle. Check all the
dispenser fittings, solenoids and pipework for leaks.
Check all bungs have been removed.
Perform test transactions to ensure flow rate is within acceptable ranges and the dispenser is
correctly measuring fuel.
If a preset is required, perform test transactions with presets and ensure they are working
correctly.
Calibrate the unit with the K-Factor (see page 16.)

Other manuals for Compac C5000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Compac C5000 and is the answer not in the manual?

Compac C5000 Specifications

General IconGeneral
BrandCompac
ModelC5000
CategoryControl Unit
LanguageEnglish

Related product manuals