18 | Piping installation
Installer and user reference guide
98
RXMLQ8 + RXYLQ10~14T7Y1B*
VRV IV system air conditioner
4P543427-1A – 2020.10
Charging refrigerant
Step 5
Proceed with manual charge
Step 6
Activate field setting [2-20]=1
Unit will start manual refrigerant charging operation.
Step 7
Open valve A
Charge remaining amount of refrigerant P (kg)
R=Q+P
Step 8
Close valve A
Push BS3 to stop manual charging
Charging is finished
Fill in the amount on the additional refrigerant charge label
Go to test run
Step 4
Connect valve A to the refrigerant charge port (d)
Open all outdoor unit stop valves
R>Q
<< Continuation of previous page
p
<
p
>
R410A
d
A
18.4.5 To charge refrigerant
Follow the steps as described below.
Pre-charging refrigerant
1 Calculate the additional amount of refrigerant to be added using the formula
mentioned in "To determine the additional refrigerant amount"[495].
2 The first 10 kg of additional refrigerant can be pre-charged without outdoor
unit operation.
If Then
The additional refrigerant amount is
smaller than 10kg
Perform steps 2+3.
The additional refrigerant charge is
larger than 10 kg
Perform steps 2~8.
3 Pre-charging can be done without compressor operation, by connecting the
refrigerant bottle to the service ports of the liquid and equalising stop valves
(open valve B). Make sure that valve A and all outdoor unit stop valves are
closed.

Table of Contents

Other manuals for Daikin VRV IV

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin VRV IV and is the answer not in the manual?

Daikin VRV IV Specifications

General IconGeneral
BrandDaikin
ModelVRV IV
CategoryAir Conditioner
LanguageEnglish

Related product manuals