3 Installation
3.1 Mechanical Installation
Select the best possible operation site by considering the
following:
•
Ambient operating temperature
•
Installation method
•
How to cool the unit
•
Position of the frequency converter
•
Cable routing
•
Power source supplying correct voltage and
necessary current
•
Motor current rating within the maximum current
from the frequency converter
•
Correct rating of external fuses and circuit
breakers
Cooling and Mounting:
•
Top and bottom clearance for air cooling must be
provided, see Table 3.1 for clearance requirements
•
Derating for temperatures starting from 45°C and
elevation 1000m above sea level must be
considered. See the equipment Design Guide for
detailed information.
Enclosure
J1-J5 J6/J7
Clearance above and below the
unit [mm]
100-200
Table 3.1 Minimum Airflow Clearance Requirements
•
Mount the unit vertically
•
IP20 units (but NOT IP21 units) allow side by side
installation
•
Improper mounting can result in over heating
and reduced performance
•
Use the slotted mounting holes on the unit for
wall mounting, when provided
•
See 8.4 Connection Tightening Torques for proper
tightening specifications.
Installation
VLT
®
AutomationDrive FC 360 Quick Guide
10 MG06A102 - VLT
®
is a registered Danfoss trademark
33