INSTALLATION
Esprit - Installation and Servicing
FLUE OUTLET
13
PREPARING THE WALL
IMPORTANT.
Ensure that, during the cutting operation, masonry
falling outside of the building does not cause damage
or personal injury.
1. Cut the flue hole (preferably with a 5" core boring
tool), ensuring that the hole is square to the wall.
Both wall faces immediately around the cut hole
should be flat.
2. Drill 3 holes with an 8mm masonry drill and
insert the plastic plugs, provided, for the wall
mounting plate.
14
SETTING THE FLUE - REAR Wall thicknesses of 200 to 426mm
Notes.
a. If using the extension ducts go to Frame 16.
b. If the stand-off frame is used it is essential add 33mm to
'X' the measured wall thickness when marking the flue
(this will allow for the fitted frame).
c. For wall thickness less than 200mm use none telescopic
b pack.
1. Measure and note wall thickness X. Refer to Frame 10.
2. Add 85mm (4") to dimension X and set telescopic flue
length as indicated in drawing.
3. Using a 3.5mm drill bit, drill two holes in outer air duct
taking care not to pierce plastic inner flue.
4. Fix to length using self tappers provided.
5. Seal out air duct using the tape provided.
15
SETTING THE FLUE - SIDE Wall thicknesses of 140 to 365mm
Note.
a. If using the extension ducts go to Frame 16.
b. For shorter flue requirements use non telescopic
b pack.
1. Measure and note wall thickness X. Refer to Frame 10.
2. Measure distance from side of boiler to inside of wall
and add to wall thickness X = L. Refer to Frame 10.
3. Add 156mm to dimension L, hand set telescopic flue
length as indicated in drawing.
4. Using a 3.5mm drill bit, drill two holes in outer air duct
taking care not to pierce plastic inner flue.
5. Fix to length using self tappers provided.
6. Seal outer air duct using the tape provided.
esp8938
X + 85
Drill hole
Adhere sealing tape
Measurement to be
taken from this point
esp8939
L + 145
Drill hole
Adhere sealing tape
Measurement to be
taken from this point
esp8816
X
Section
through wall
Note. Check all of the hole
positions before drilling.
Side flue only
5" diameter hole
Rear flue only
5" diameter hole

Other manuals for IDEAL he24

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL he24 and is the answer not in the manual?

IDEAL he24 Specifications

General IconGeneral
BrandIDEAL
Modelhe24
CategoryBoiler
LanguageEnglish

Related product manuals