5. Initial Start Up procedure:
5.1 Verification of different voltage level sources:-
5.1.1 Before Control Panel Power Up, Disconnect all the Control Terminal wiring which are connected to
MCTC-MCB-G of NICE 1000
5.1.2 Switch on the main power supply Circuit Breaker; check the incoming voltage level between R vs S, S
vs T, T vs R and R S T with respect to N at Lift Control Panel using Multi meter
MULTIMETER
5.1.3 Make sure that the Incoming Voltage level satisfies the specification
5.1.4 Turn ON the Control Panel Circuit Breakers one by one and check the voltage level simultaneously;
Make sure that the voltage levels are within specified limits (Refer Electrical Drawing)
ON

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Inovance NICE1000 and is the answer not in the manual?

Inovance NICE1000 Specifications

General IconGeneral
BrandInovance
ModelNICE1000
CategoryController
LanguageEnglish

Related product manuals