Address Name / seng range / [default seng] Informaon
0x2022:039 Device commands: Load TA default sengs
All parameter changes made by the user are lost during this process!
When the device command has been executed successfully, the value
0 is shown.
0 O / ready Only status feedback
1 On / start All controller parameters are reset to the default seng. Parameters
that are declared separately in the applicaon are set to the
corresponding standard values from the technology applicaon.
2 In progress Only status feedback
3 Acon cancelled
4 No access
5 No access (Device disabled)
5.13 Start PLC program
How to start the PLC program:
Precondions
The »PLC Designer« is connected to the controller and the current PLC program has
already been transferred.
1.
Use the menu command Debug -->Start or the funcon key <F5> to start the PLC program.
The following table provides informaon on the current state of the PLC project.
LED status display
"RUN" LED (yellow/green) Meaning
PLC project is being loaded.
PLC project is stopped.
PLC project is started.
5.14 Generate boot applicaon
An executable PLC program can be executed when the controller is started.
To do so, a boot applicaon must have been created using the »PLC-Designer« The boot
applicaon also stores the parameter set on the SD card of the controller.
Commissioning
Start PLC program
Reset parameters to default
24

Table of Contents

Other manuals for Lenze c550

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lenze c550 and is the answer not in the manual?

Lenze c550 Specifications

General IconGeneral
BrandLenze
Modelc550
CategoryController
LanguageEnglish

Related product manuals