Commissioning
20
During initial commissioning, the following settings must be carried
out. You will be asked to programme settings one after the other
automatically, and currently selected values will have a tick
beside them. The commissioning process follows a set procedure
which cannot be interrupted.
The commercial dishwasher will guide you automatically through the
steps required.
Reactivation is carried out during the first programme following
commissioning.
If the first programme after commissioning is not completed and
the commercial dishwasher is then switched off, the initial
commissioning process must be carried out again.
The following options (with the exception of “Plumbing
connections”) can be altered subsequently by selecting the
“Settings ”menu and “Further settings”.
Switching on
The dishwasher must be connected to the electrical supply.
Press the button until the button's LED lights up.
Setting the
language
The commissioning process automatically begins at the language
setting screen, where you will be prompted to set the display
language.
Language
,
;
(
english (GB)
deutsch
Use the and arrow buttons to select the desired language and
confirm your choice with the OKbutton.