TWP/TWB200 – TWP/TWB9000
22
START UP
Verify all piping and electrical connections are secure. Do not power the dryer at this time.
Start the compressor and pressurize the air system, bypassing the dryer.
Slowly pressurize the dryer by opening the inlet isolation valve. It is important to allow the dryer to slowly
pressurize to prevent uidization of the desiccant bed. Rapid pressurization can also cause damage to the
vessel internal screens and lter elements.
The dryer must be started without the mufers installed. This will expedite removal of excess desiccant dust and
prevent premature clogging of the mufers.
CAUTION: USE EAR AND EYE PROTECTION WHEN OPERATING THE DRYER WITHOUT MUFFLERS. EXCESSIVE
NOISE WILL BE CREATED. DUST AND PARTICLES FROM THE SURROUNDING AREA MAY BECOME AIRBORNE.
OPERATION WITHOUT MUFFLERS EXCEEDS OSHA LIMITS.
Open the control air ball valve.
Push in the emergency stop button.
Power up the dryer. Check rotation of blower by pushing in contactor manually. If opposite of the ow direction
arrow, switch the two leads.
Pull the emergency button out.
Start in Heatless - Touch the START IN HEATLESS OPERATION button from the controller’s SERVICE screen to
start the dryer. The dryer will initially ensure that vessels are pressurized, then will begin by blowing down one
of the vessels while placing the opposite ‘drying’ vessel online. If you do not want the dryer to begin cycling
automatically, close the control air ball valve. This will prevent the inlet and exhaust valves from switching. In this
situation, a bad blowdown alarm will occur which must be reset from the control panel after re-opening the control
air ball valve.
The dryer can be run in the heatless mode for two or three cycles to quickly remove desiccant dust caused by
shipping or lling the unit. This also serves to verify that the vessels are switching normally, and to allow resolving
any issues with system pressure before applying heat the regeneration process.
Switch to Heated - When you are ready to switch the dryer to HEATED regeneration operation, simply touch the
START IN HEATED OPERATION button from the controller’s Service screen. The dryer will immediately repressurize,
then switch towers and start HEATED regeneration on the opposite vessel.
Install the exhaust mufers on the dryer.
Check Purge Pressure - For TWP dryers, verify the purge pressure setting is correct for the operating conditions.
The purge pressure setting must be set to the factory advised setting while using the dewpoint demand feature.
The purge pressure must be set while in the Heated Regeneration State. Do not adjust the purge pressure when
operating in the heatless backup timing conguration.
Heating - Verify that the heater contactor(s) pull in and the purge air temperature value on the controller screen
begins to rise. If the dryer is blower type, then the blower will also be running at this time.
Over-Temp - There is a redundant over-temperature module inside the control cabinet that is preset at the factory to
650°F. This module monitors a thermocouple for purposes of independently sensing an over-temperature condition.
In addition, there is an over-temp setting, also preset the factory to 650°F, accessed from the ADVANCED SETTINGS
screen on the controller. This setting is associated with the purge temperature sensor.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Parker Airtek TWB800 and is the answer not in the manual?

Parker Airtek TWB800 Specifications

General IconGeneral
BrandParker
ModelAirtek TWB800
CategoryDryer
LanguageEnglish

Related product manuals