Diagnostics: Displays the Isolation status and power optimizer status
screens. Refer to
https://www.solaredge.com/sites/default/files/application_note_
isolation_fault_troubleshooting.pdf.
Activate Standby Mode: Enables/disables Standby Mode - for remote
commissioning.
Grid Protection: Available in specific countries. Enables viewing and setting grid
protection values.
Board Replacement: Backs up and restores the system parameters, including energy
counters; Used during board replacement according to the instructions supplied
with replacement kits.
Information
From the Commissioning menu, select Information to view and set various system
settings, as described below.
CPU Version: The communication board firmware version
DSP 1/2 Version: The digital board firmware version
NOTE
Please have these numbers ready when you contact SolarEdge Support.
Serial Number: The inverter serial number as appears on the enclosure sticker
Error Log: Displays the last five errors, and enables resetting (clearing) the log
Warning Log: Displays the last five warnings, and enables resetting (clearing) the
log
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on each
inverter.
2. Select Status and verify that inverter is operating and producing power (see also
Viewing System Status
on page 48).
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.