The foundation must guarantee solid and safe positioning of the inverter. It must
provide the load-carrying capacity necessary to cope with the weight
of the inverter.
SG100K3 Grid-Connected Photovoltaic Inverter is designed for indoor use only and
must be placed to a level concrete floor or pad.
Any existing unevenness, depressions or slope must be corrected prior to installation.
Prior to place the inverter, users should bear in mind that the wires should enter the
inverter from
and through the
.
The installation ambience requirements
Installation location must be dry, including no expected condensation.
Maintain a minimum of 100 mm clearance in back, 600mm in front and 600mm in
top of the SG100K3 for proper ventilation and installation maintenance operation.
Note
::
The space from the top of the enclosure to the installation site
ceiling must be left enough for ventilation and maintenance;
otherwise maintenance personnel cannot open the top panel.
To place the enclosure on the mounting surface:
1. Make sure the mounting surface is level.
2. Move the SG100K3 into position.