Performance tests
Analog amplitude accuracy
Required equ ipment Prerequisites
Digital multimeter
BNC-dual banana adapter
50 Ω BNC feed-through terminator
SMA female-BNC male adapter
50 Ω SMA terminator
AWG preparation and load test waveforms
(See page 42.)
Termination resistance measurement
procedure (Term R) (See page 44.)
Before starting this procedure, ensure you have the “Term R” value used in the
calculations. (See page 44, Termination resistance measurement.)
DC High BW output path
1. Click the Reset to Default Setup button in the toolbar .
2. Press the AWG front panel All Outputs Off button (or click All Outputs Off
on the Home screen) to disable the outputs (front panel light on).
3. Load the test waveforms PV_DC_Plus.wfmx and PV_DC_Minus.wfmx
into the Waveform List.
NOTE. Test waveforms are located at
C:\Pr
ogram F iles\Tektronix\AWG5200\Samples\PV.
4. From the Waveform List window, assign the test waveform
PV_D
C_Plus.wfmx to Channel 1 .
5. Connect the CH 1 (+) connector from the AWG to the HI and LO inputs of
the
digital multimeter.
Use a 50 Ω SMA cable , a BNC -SMA adapter, a 50 Ω BNC feed-through
te
rminator, and a BNC dual banana adapter.
6. Terminate the CH 1 (–) connector on the AWG with a 50 Ω SMA terminator.
AWG5200 Series Technical Reference 45