20 CGWF-SVX01A-EN
Installation Mechanical
Lifting Procedure for 60 Ton Units
WARNING
Unit Lifting Capacity!
The capacity of the lifting equipment sued must exceed etc. Then end
with failure to use properly sized lifting equipment could result in death
or serious injury or equipment damage.
WARNING
Improper Unit Lifting!
Follow the lifting procedure detailed below. Failure to follow the proper
lifting procedure could result in death or serious injury or equipment
damage.
1. Dismantle shipping crate.
2. Remove the unit from the shipping skid. If absolutely necessary, the chiller can be
pushed or pulled across a smooth surface as long as it is bolted to the shipping
skid.
3. Attach chains or cables to lifting beam.The total lifting weight, lifting weight distri-
bution and required lifting beam dimensions are shown in Figure 5. Lifting beam
crossbars must be positioned so lifting cables do not contact the side of the unit.
CAUTION
Unit Damage!
To prevent unit damage, position lifting beam crossbars so that cables
do not contact the unit.

Table of Contents

Other manuals for Trane CCAF

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Trane CCAF and is the answer not in the manual?

Trane CCAF Specifications

General IconGeneral
BrandTrane
ModelCCAF
CategoryChiller
LanguageEnglish

Related product manuals